PPI Schedule 1/22/2022- 1/28/2022

Please be advised that Performance Pipeline Inc. will be working in the following areas:


Main Line Lining

Saturday- Washington Street in Red Hill Borough

Monday - 3rd Street & Washington Street in Red Hill Borough

Tuesday- Dotts Street & Main Street in Pennsburg Borough

Wednesday - Macoby Street, Main Street & Pennsburg Manor Row in Pennsburg

*Thursday & Friday may entail work that got moved due to weather & equipment issues, will update early next week

Vac A Tee Installation Monday, Tuesday, Wednesday

In Pennsburg Borough Montgomery Ave

Main Street

Penn Street

Lake Lane

Seminary Road

Lakeview Terrace


In Red Hill Borough Jefferson Street


Lateral Launching Monday, Tuesday, Thursday

In Red Hill Borough Bitting Alley

11th Street

Second Street

Cindy Lane


17 views0 comments

Recent Posts

See All

Please be advised that Performance Pipelining Inc. will be working in the following areas during the week of May 2nd: Vac-A-Tee Installation Graber Alley Restoration in Red Hill Borough on Monday, May

Please be advised that Performance Pipelining Inc. will be working in the following area during the week of April 25th: Vac-A-Tee installation Main Street & Jefferson Street in Red Hill Borough Dotts