Search

PPI Schedule: Week of April 25th

Please be advised that Performance Pipelining Inc. will be working in the following area during the week of April 25th:


Vac-A-Tee installation

Main Street & Jefferson Street in Red Hill Borough


Dotts Street in Pennsburg Borough


Lateral Launching

State Street, Blaker Drive, Colonial Drive, Hamilton Road

in East Greenville Borough


All properties that will be impacted will receive a notice of their front door on Monday prior to work being done.

6 views0 comments

Recent Posts

See All

Please be advised that Performance Pipelining Inc. will be working in the following areas during the week of May 2nd: Vac-A-Tee Installation Graber Alley Restoration in Red Hill Borough on Monday, May

Please be advised that Advanced Rehabilitation Technology (ART) will be working to rehabilitate manholes on School Alley and Jefferson Street in East Greenville Borough during the week of April 18th.