T-Liner Installation

Monday, December 6th through Wednesday, December 8th.

4th Street & Jefferson Street in East Greenville


Tv & Cleaning

Washington Street & Hickory Street in East Greenville


Manhole Raise to Grade

West Side Alley & 5th Street, Dotts Street in Pennsburg

Blaker & Morris Road in East Greenville

Connection Inspections: PPI will continue connection inspections for all homes connected to the Hickory Alley mainline. Residents are urged to contact PPI as soon as possible to schedule an appointment.