PPI Schedule Week of September 12th

Please be advised the Performance Pipelining Inc. will be working in the following areas during the week of September 12th. The schedule may change due to weather or delays.



Monday 9/12

  • Penn Street in Pennsburg Borough

  • Main Street in East Greenville Borough 1000 Block of Jefferson Street in Red Hill Borough

Tuesday 9/13

  • Dotts Street, Jackson Street, Washington Street in Pennsburg Borough

  • 1000 Block of Jefferson Street & W. 11th Street in Red Hill Borough

Wednesday 9/14

  • Cherry Street & State Street in East Greenville Borough

  • Seminary Street in Pennsburg Borough

Thursday 9/15

  • Red Hill Road in Red Hill Borough

  • Seminary Street in Pennsburg Borough



Crews will also be televising 3rd Street, 4th Street, Cherry Street, School Alley in East Greenville Borough & Long Alley in Pennsburg Borough.



4 views0 comments

Recent Posts

See All

Please be advised that Performance Pipelining Inc. will be working in the following areas during the week of September 26th: In Pennsburg Borough Monday – 9/26 -Lake Lane Tuesday- 9/27- Montgomery Ave

Low Income Household Water Assistance (LIHWAP) program funds are nearly depleted. The last day that the program will accept applications will be October 28, 2022. To apply for LIHWAP click HERE

Please be advised that Performance Pipelining Inc. will be lining the main sewer line on Bitting Alley & Graber Alley from Tuesday, September 20th - Friday, September 23rd between the hours of 7AM - 4